This volume presents practical guidance for the government manager on earned value management (EVM), from basic calculations to how to find the most useful information online. Emphasis is on the relevant reports that contractors are required to submit to the federal government as part of their compliance with mandated EVM on projects. Because the data submitted on reports do not translate automatically into recommendations for actions to be taken, information is included on how to analyze and evaluate contractor reports. This book is a must-read for understanding EVM on government projects.
Frequently asked questions
How do I cancel my subscription?
Can/how do I download books?
At the moment all of our mobile-responsive ePub books are available to download via the app. Most of our PDFs are also available to download and we're working on making the final remaining ones downloadable now. Learn more here.
What is the difference between the pricing plans?
Both plans give you full access to the library and all of Perlegoâs features. The only differences are the price and subscription period: With the annual plan youâll save around 30% compared to 12 months on the monthly plan.
What is Perlego?
We are an online textbook subscription service, where you can get access to an entire online library for less than the price of a single book per month. With over 1 million books across 1000+ topics, weâve got you covered! Learn more here.
Do you support text-to-speech?
Look out for the read-aloud symbol on your next book to see if you can listen to it. The read-aloud tool reads text aloud for you, highlighting the text as it is being read. You can pause it, speed it up and slow it down. Learn more here.
Is The Government Manager's Guide to Earned Value Management an online PDF/ePUB?
Yes, you can access The Government Manager's Guide to Earned Value Management by Charles I. Budd, Charlene S. Budd in PDF and/or ePUB format, as well as other popular books in Business & Governmental Accounting. We have over one million books available in our catalogue for you to explore.
Information
Chapter 1
THE FUNDAMENTALS OF EVM
Earned value management (EVM) as we know it today might not exist without the federal governmentâs instigation and support. In the 1960s, the U.S. government commissioned a project reporting system composed of 35 requirements called the cost/schedule control systems criteria (C/SCSC). The objective of that system was to provide a common basis for reporting and decision-making by both the project initiator and the project contractor. That is, the project owner (the federal government) needed information that established a valid relationship among cost, schedule, and technical requirements in a summarized and meaningful format from the people actually performing project work so timely decisions could be made.
After the U.S. government spearheaded the development of objective project reporting, industry groups joined the effort and C/SCSC was modified into todayâs 32 EVM criteria. The first industry-approved EVM standard, ANSI/EIA 748-A, was published by the Government Electronics and Information Technology Association (GEIA) in 1998 and adopted by the federal government in 1999. In 2007, ANSI/EIA-748-B (the EVM standard) was approved. Through association mergers, GEIA later became a part of TechAmerica. An ANSI-accredited national standards developer, TechAmerica released ANSI/EIA-748-C in March 2013. The ANSI/EIA-748 version in force at the time contracts are signed, as elaborated and interpreted by various government documents, is the version that governs contractor EVM systems.
Manager Alert
ANSI/EIA-748 has been through several revisions; the version in force when a contract is signed is the governing version for that contract.
EARNED VALUE DEFINED
An earned value management system (EVMS) is universally defined as a project management system that, at a minimum, complies with the 32 criteria set forth in ANSI/EIA-748. âEarned valueâ is the primary metric for reporting progress on a project or program. Work âearnedâ is the amount of budgeted work scheduled that has been completed.
EVMS is an integrated project management system that includes the planning and execution of a project or program. From a high-level view, as shown in Table 1-1, it seems quite simple.
TABLE 1-1
Basic Elements of an EVMS
Basic Elements of an EVMS
Project Phase | Description | Requirement |
Planning | A detailed definition of the work elements and their relationships that are required to complete the projectâs objectives. | Work Breakdown Structure |
Assignment of the organizational entities for work performance. | Organizational Breakdown Structure | |
A schedule of the work to be performed with milestones and deliverables. | Project Plan | |
Integration of the cost and schedule in a baseline plan. | Time-phased Baseline Budget | |
Execution | Accumulation of costs. | Actual Costs Incurred |
Measurement of progress. | Earned Value | |
Analysis of variances from the plan. | Cost Variance; Schedule Variance | |
Reporting to management. | IPMR* Formats 1â7 | |
Forecasting of schedule and cost completion data. | Estimate to Complete; Estimate at Completion | |
Disciplined maintenance of the plan data and proposed revisions. | Change Control Plan |
* Integrated Management Report Program
Manager Alert
âEarned valueâ is the metric that represents the amount of scheduled project work that actually has been completed.
The Department of Defense (DoD) presents a complete description of EVMS in Part 1, Section 1, of its 2006 Earned Value Management Implementation Guide:
Earned Value Management (EVM) is a program management tool that integrates the technical, cost, and schedule parameters of a contract. During the planning phase, an integrated baseline is developed by time phasing budget resources for defined work. As work is performed and measured against the baseline, the corresponding budget value is âearned.â From this earned value metric, cost and schedule variances can be determined and analyzed. From these basic variance measurements, the program manager (PM) can identify significant drivers, forecast future cost and schedule performance, and construct corrective action plans to get the program back on track. EVM therefore encompasses both performance measurement (i.e., what is the program status) and performance management (i.e., what we can do about it). EVM is program management that provides significant benefits to both the Government and the contractor.1
EVM ADOPTION
U.S. government entities, such as DoD, the National Aeronautics and Space Administration (NASA), the Department of Energy, and the Office of Management and Budget (OMB), as well as international government entities, have set the basic definitions, concepts, and requirements for EVMS through their contract management agencies. Many implementation and intent guides have been published and revised, but the basic EVM requirements (with the exception of some rewording to clarify meaning) have remained unchanged.
Although DoD will continue to review contractorsâ EVM systems, it encourages contractors and the entire industrial sector to assume growing responsibility for EVM processes. Numerous EVM consulting and training assistance groups stand ready to assist in EVM implementation, execution, reporting, or any other facet.
GOVERNMENT-REQUIRED USE
In April 2013, DoD issued a supplement to the Defense Federal Acquisition Regulation (DFARS) in which Subpart 234.2 further confirmed the system requirements for use of an EVMS. Those requirements include the following:
- Optional compliance with ANSI/EIA-748 for cost or incentive contracts and subcontracts valued at less than $20 million, with a decision to comply voluntarily with EVM guidelines documented in the contract file along with a risk-benefit analysis
- Compliance with ANSI/EIA-748 for cost or incentive contracts for contracts and subcontracts valued at $20 million or more
- âConfirmedâ (determined by the cognizant federal agency) compliance with ANSI/EIA-748 for cost or incentive contracts for contracts and subcontracts valued at $50 million or more
- Strong discouragement (a waiver is required) of the use of ANSI/EIA-748 for firm-fixed-price contracts for contracts and subcontracts of any value.
Other sections of Subpart 234.2 cover the details of exactly how the contractorâs EVMS will be evaluated, how deficiencies are noted for correction, and how a final âacceptâ or ârejectâ decision is made. Subpart 234.2 also describes how inspection results at various stages of the investigation must be reported.
Manager Alert
Government requirements for a contractorâs use of EVM vary depending on the size and type of contract.
Special provision may be made for temporary use of EV systems that are not compliant with ANSI/EIA-748, but cost or incentive contracts valued at $20 million or more must follow the provision at 252.234â7001 (not FAR 52.234-2 and FAR 52.234-3).
THE 32 EVMS CRITERIA SUMMARIZED
The EVMS criteria are usually divided into five sections:
- Organization
- Planning and budgeting
- Accounting considerations
- Analysis and management reports
- Revisions and data maintenance.
The 2006 revision of the ANSI/EIA criteria added âschedulingâ to the second section; the sections of the 2013 revision remain essentially unchanged.
Manager Alert
The 32 EVM criteria are generally divided into sections that represent five basic project management concepts.
This five-step division is intended to address basic management concepts, but many of the concepts overlap. The criteria are presented fully in Appendix I with the latest version notations. The following are the...