The Scheduling Maturity Model
eBook - ePub

The Scheduling Maturity Model

  1. English
  2. ePUB (mobile friendly)
  3. Available on iOS & Android
eBook - ePub

The Scheduling Maturity Model

About this book

The Scheduling Maturity Model is intended to provide a defined means of establishing and improving scheduling capability as part of an organisation's project, programme or enterprise control processes. Moreover, it is intended to support project and programme teams and organisations by improving an important part of their overall project controls capability.

Frequently asked questions

Yes, you can cancel anytime from the Subscription tab in your account settings on the Perlego website. Your subscription will stay active until the end of your current billing period. Learn how to cancel your subscription.
No, books cannot be downloaded as external files, such as PDFs, for use outside of Perlego. However, you can download books within the Perlego app for offline reading on mobile or tablet. Learn more here.
Perlego offers two plans: Essential and Complete
  • Essential is ideal for learners and professionals who enjoy exploring a wide range of subjects. Access the Essential Library with 800,000+ trusted titles and best-sellers across business, personal growth, and the humanities. Includes unlimited reading time and Standard Read Aloud voice.
  • Complete: Perfect for advanced learners and researchers needing full, unrestricted access. Unlock 1.4M+ books across hundreds of subjects, including academic and specialized titles. The Complete Plan also includes advanced features like Premium Read Aloud and Research Assistant.
Both plans are available with monthly, semester, or annual billing cycles.
We are an online textbook subscription service, where you can get access to an entire online library for less than the price of a single book per month. With over 1 million books across 1000+ topics, weโ€™ve got you covered! Learn more here.
Look out for the read-aloud symbol on your next book to see if you can listen to it. The read-aloud tool reads text aloud for you, highlighting the text as it is being read. You can pause it, speed it up and slow it down. Learn more here.
Yes! You can use the Perlego app on both iOS or Android devices to read anytime, anywhere โ€” even offline. Perfect for commutes or when youโ€™re on the go.
Please note we cannot support devices running on iOS 13 and Android 7 or earlier. Learn more about using the app.
Yes, you can access The Scheduling Maturity Model by Association for Project Management (APM) in PDF and/or ePUB format, as well as other popular books in Business & Project Management. We have over one million books available in our catalogue for you to explore.
Annex A โ€“ Scheduling Maturity Model Questions
image
image
image
image
image
image
image
image
image
image
image
image
image
image
image
image
image
image
image
image
table class="source-table" cellspacing="0">

ATTRIBUTE MATURITY LEVEL

 

1

2

3

4

5

As Is

To Be

 

1. Use of Scheduling Process & compliance to contractual requirements

 

 

The scheduling process is ad-hoc and not coordinated. There are no documented scheduling guidelines or standards. The schedule
complies with most,
if not all, applicable contractual requirements for schedules.

The scheduling process is ad-hoc and not fully coordinated. Some local scheduling guidance in place. The schedule complies with all applicable contractual requirements for schedules.

The scheduling process is structured and focused. It utilises a set of standard, documented, and controlled processes for the preparation and publication of schedules. Reviews/audits are periodically conducted to ensure documented processes are being followed and contractual requirements are being met.

The scheduling process is followed by the whole team. It utilises metrics to monitor the health of the scheduling processes and performs scheduled self-assessments, as documented, to ensure processes are being followed.

All projects and contracts within the programme adhere to a consistent documented scheduling process. All project teams follow the same process. Poor process performance is isolated, and corrective action plans are implemented. Root cause analysis is performed and corrective actions are implemented when scheduling process issues are identified. Process improvements are identified and fed into the Project Management Function.

 

 

 

2. Scheduling tools are suited to enterprise needs

 

 

Process and toolset

Schedules are generated by hand or PC graphics software.

Master and team schedules are developed manually using one or more databases. Integration between team schedules is managed separately from the scheduling toolset.

Project management software (networking and resource loading capability) is used for non-recurring schedules or other appropriate schedules. Management-recognised standard software tools are used. All schedules are integrated in a ‘singlesource’ database with manual links to other systems. Schedules are manually linked to other systems as part of performance management.

All schedules are integrated by automation into a ‘single-source’ database. There is automated linkage between the ‘singlesource’ schedule database and other systems containing schedule data. Schedule performance metrics exist in the MIS. Appropriate scheduling tools are utilised based on the size and complexity of programme.

Colour-coded (or other differentiator) schedule metrics with drill-down capability are generated from the scheduling database for the MIS. Presentation graphics are generated from the scheduling database. Major supplier detailed schedule data is transmitted via electronic data interchange (or other automated technology) and is electronically integrated into the programme schedule. Scheduled/network templates are used for standard sequences of activities.

 

 

 

3. Schedule analysis products are current and used throughout the enterprise

 

 

Schedule update is ad-hoc. Clearly defined ownership of schedule elements is not always appropriate.

Schedules are updated and statused on a regular published update cycle per project management and contractual requirements. (Estimated/forecast dates are projected for milestones and activities which are past due or with negative float.)

Schedule performance metrics are prepared and reviewed with/by Team Leaders on a regular (or other documented) basis. (Examples include: Current schedule vs. actual milestones, deficient item listings, supplier status and impact of late items.)

The following types of metrics are also reviewed regularly. Examples include: an overall schedule performance summary/variance analysis; network and Critical Path Analysis.
The project utilises float as an indicator of schedule health.

Predictive analysis is reported in regular meetings and is utilised in the decision-making process by the project management team.

 

 

ATTRIBUTE MATURITY LEVEL

 

1

2

3

4

5

As Is

To Be

 

4. Defined organisation/roles and responsibilities

 

 

 

No consideration of an Organisation Breakdown Structure (OBS). Roles and responsibilities are not documented.

Roles are defined but responsibilities are not. No OBS is identified in the schedule.

All activities are assigned to an element of the OBS. A documented correlation exists between the WBS and OBS, utilising the RAM.

Organisational issues are subject to change control. OBS and RAM are maintained within the scheduling tool to reflect the current standard.

The project OBS includes cross-references to other OBS at the enterprise level.

 

 

 

5. Capturing project and customer requirements

 

 

Schedule structure and hierarchy

There are no formal methods for capturing customer requirements – e.g. WBS or only an outline WBS or PBS.

Scope is documented, defined and decomposed into meaningful, manageable elements.
A recognised WBS is established.

All authorised work elements are defined for the project. A WBS is used in this process and captures the full scope of work.

A systematic process decomposes project requirements and identifies the scope of work necessary to deliver these requirements.
The scope of work is under configuration control. The link between customer requirements and WBS elements is clearly defined.

All customer requirements have been decomposed into the WBS and associated work scope. This mapping is transparent and under configuration control. Changes to the technical baseline or requirements are properly managed through a documented, integrated change control process.

 

 

6. Basis of Estimate

 

 

Project estimates are produced without Project Team consultation and without documented procedures.

There is a record of estimates but formal estimating techniques and processes have not been applied. Estimating assumptions are not fully documented.

A formal structured estimate has been generated following standard estimating procedures. All estimating assumptions are fully documented.

Estimates are based on previous project norms, historical data, or parametric estimating. All estimating assumptions are fully documented.

The estimate has been reviewed by an independent authority. Upon completion of projects the actual performance data is used to inform future estimates/update project norms. Full ownership and authorisation of the estimate is shared by all relevant ...

Table of contents

  1. Cover
  2. Copyright
  3. Table of contents
  4. Preface
  5. Foreword
  6. Acknowledgements
  7. Applicability
  8. Introduction
  9. Fundamental Concepts
  10. How is the Maturity Model used for Assessment?
  11. What are the Benefits?
  12. Assessment โ€“ The General Process
  13. Implementation Roadmap โ€“ Maturity Levels and Stages
  14. Scheduling Compass Guidance Information
  15. Process and Toolset
  16. Schedule Structure and Hierarchy
  17. Schedule Integration
  18. Schedule/Resource/Cost Integration
  19. Schedule Risk
  20. Schedule Update and Maintenance
  21. Environment
  22. Annex A โ€“ Scheduling Maturity Model questions
  23. Annex B โ€“ Glossary
  24. Annex C โ€“ Abbreviations and Acronyms
  25. Annex D โ€“ Related Documents
  26. Annex E โ€“ Figures and Tables
  27. Back Cover