Understanding NEC3: Engineering and Construction Short Contract
eBook - ePub

Understanding NEC3: Engineering and Construction Short Contract

A Practical Handbook

  1. 182 pages
  2. English
  3. ePUB (mobile friendly)
  4. Available on iOS & Android
eBook - ePub

Understanding NEC3: Engineering and Construction Short Contract

A Practical Handbook

About this book

As usage of the NEC (formerly the New Engineering Contract) family of contracts continues to grow worldwide, so does the importance of understanding its clauses and nuances to everyone working in the built environment. This set of contracts, currently in the third edition, is different to others in concept as well as format, so users may well find themselves needing a helping hand along the way.

Understanding the NEC3 Engineering and Construction Short Contract uses plain English to lead the reader through the contract's key features, including:

  • the use of early warnings
  • programme provisions
  • payment
  • compensation events
  • preparing and assessing tenders

Common problems are signalled to the reader throughout, and the correct way of reading each clause explained. In addition, the things to consider when deciding between the ECSC and the longer Engineering and Construction Contract are discussed in detail.

Written for professionals without legal backgrounds, by a practicing construction contract consultant, this handbook is the most straightforward, balanced and practical guide to the NEC3 ECSC available. An ideal companion for Employers, Contractors, Project Managers, Supervisors, Engineers, Architects, Quantity Surveyors, Subcontractors, and anyone else interested in working successfully with the NEC3 ECSC.

Trusted byĀ 375,005 students

Access to over 1.5 million titles for a fair monthly price.

Study more efficiently using our study tools.

Information

Publisher
Routledge
Year
2014
Print ISBN
9781138132023
eBook ISBN
9781317702122

1 Early warnings

1.1 Introduction

Early warnings are covered within the Engineering and Construction Short Contract (ECSC) by Clauses 16.1 and 16.2.
Early warnings are an essential and valuable risk management tool within the NEC3 contracts. The ECSC obliges the Contractor and the Employer to notify each other as soon as either becomes aware of any matter which could affect the project in terms of time, cost or quality, bringing into the open as early as possible any matter which could adversely affect the outcome of the contract.
Under Clause 16.1 the Contractor and the Employer give an early warning by notifying the other as soon as either becomes aware of any matter which could:
• increase the total of the Prices.
• Increase the Price of the works.
• • delay Completion.
• Delay Completion of the whole of the works.
• • impair the performance of the works in use.
• Have a qualitative effect on the finished project.
This sometimes causes confusion, but let us look at an example. On an Employer-designed project, the Contractor is instructed to install a particular type of pump. If the Contractor knows from experience that that pump would probably not be sufficient to meet the Employer’s requirements once the works are taken over, then the Contractor should give an early warning stating his concern.
The Contractor may also give an early warning by notifying the Employer of any other matter which could increase his total cost.
One could query whether a matter which could increase the Contractor’s cost, but not affect the Price, should be an early warning matter, or for that matter, whether it should be anything to do with the Employer, particularly if the Contractor is not looking to recover this additional cost through the contract, but the words are ā€˜the Contractor may give an early warning’, so he is not obliged to do so.
Under Clause 16.2, after an early warning has been given, the Parties have an obligation to discuss the problem and decide how best to resolve, avoid or reduce it.
The Parties are expressly not required to give an early warning for which a compensation event has previously been notified.
The early warning procedure obliges people to be ā€˜proactive’, dealing with risks as soon as the Parties become aware of them, rather than ā€˜reactive’, waiting to see what effect they have, then trying to deal with them when it is often too late. Encouraging the early identification of problems by both Parties puts the emphasis on joint solution finding rather than blame assignment and contractual entitlement.
It is one of the most important and valuable aspects of the contract and it is perhaps surprising that, whilst some other contracts refer to an early warning process, only the NEC contracts set out in clear detail what the parties are obliged to do, with appropriate sanctions should the parties not comply (Clauses 61.3 and 63.5).

1.2 Notifying early warnings

The contract requires (Clause 13.1) that all communications under the contract must be in writing, so early warnings should not be a verbal communication such as a telephone conversation. If the first notification is a telephone conversation, or a comment in a site meeting, it should be immediately confirmed in writing to give it contractual significance (Figure 1.1).
There are some key words within the obligation to notify:
• ā€˜The Contractor and the Employer’ – no one else has the authority or obligation to give an early warning. The Employer is therefore notifying on behalf of himself, and anyone who represents him within the contract, e.g. Designers. The Contractor is notifying on behalf of himself, his Subcontractors, his Designers (if appropriate), and again many possible others whom he represents under the contract. Early warnings should be notified by the key people acting for the Parties.
Employers are often criticised for seeing early warnings as something the Contractor has to do, and in fact most early warnings are actually issued by the Contractor. However, the Contractor and the Employer are obliged to give early warnings each to the other, so it is critical that Employers play their part in the process.
As an example, if the Employer becomes aware that he will be late in delivering some design information to the Contractor, he should issue the early warning as soon as he becomes aware that the information will not be delivered to the Contractor, not wait and subsequently blame the Contractor for not giving an early warning stating that he has not received the information!
image
Figure 1.1 A typical example of an early warning notice template.
• ā€˜As soon as’ – means immediately. There are a number of clauses within the contract that deal with the situation where the Contractor did not give an early warning. Whilst the party who gives the early warning must do so as soon as he becomes aware of the potential risk, the other party should respond as soon as possible and in all cases within the period for reply in Contract Data Part 1.
• ā€˜Could’ – not ā€˜must’, ā€˜will’ or ā€˜shall’. Clearly there is an obligation to notify even if it is only felt something may affect the contract, but there is no clear evidence that it will.
The Employer enters early warning matters in the Risk Register. As stated previously, early warning of a matter for which a compensation event has previously been notified is not required.
It must be emphasised that early warnings are not the first step towards a compensation event, as is often believed. Early warnings feature in a completely separate section of the contract and, in fact, the early warning provision is intended to prevent a compensation event occurring or at least to lessen its effect. It can also be used to notify a problem which is totally the risk of the notifier. It is also worth mentioning that early warnings are a notice of a future risk, not a past one.
The Parties are not required, nor is it of any value, to notify a risk that has already happened.
Box 1.1 Example
One week before the Completion Date on a small refurbishment project, the Contractor is informed by his electrical Subcontractor that they have insuf...

Table of contents

  1. Cover
  2. Half Title
  3. Title Page
  4. Copyright Page
  5. Table of Contents
  6. List of figures
  7. Preface
  8. Acknowledgements
  9. Introduction
  10. 1 Early warnings
  11. 2 Design
  12. 3 Time
  13. 4 Defects
  14. 5 Payment
  15. 6 Compensation events
  16. 7 Title
  17. 8 Indemnity, insurance and liability
  18. 9 Termination
  19. 10 Disputes
  20. 11 Tendering
  21. Index

Frequently asked questions

Yes, you can cancel anytime from the Subscription tab in your account settings on the Perlego website. Your subscription will stay active until the end of your current billing period. Learn how to cancel your subscription
No, books cannot be downloaded as external files, such as PDFs, for use outside of Perlego. However, you can download books within the Perlego app for offline reading on mobile or tablet. Learn how to download books offline
Perlego offers two plans: Essential and Complete
  • Essential is ideal for learners and professionals who enjoy exploring a wide range of subjects. Access the Essential Library with 800,000+ trusted titles and best-sellers across business, personal growth, and the humanities. Includes unlimited reading time and Standard Read Aloud voice.
  • Complete: Perfect for advanced learners and researchers needing full, unrestricted access. Unlock 1.5M+ books across hundreds of subjects, including academic and specialized titles. The Complete Plan also includes advanced features like Premium Read Aloud and Research Assistant.
Both plans are available with monthly, semester, or annual billing cycles.
We are an online textbook subscription service, where you can get access to an entire online library for less than the price of a single book per month. With over 1.5 million books across 990+ topics, we’ve got you covered! Learn about our mission
Look out for the read-aloud symbol on your next book to see if you can listen to it. The read-aloud tool reads text aloud for you, highlighting the text as it is being read. You can pause it, speed it up and slow it down. Learn more about Read Aloud
Yes! You can use the Perlego app on both iOS and Android devices to read anytime, anywhere — even offline. Perfect for commutes or when you’re on the go.
Please note we cannot support devices running on iOS 13 and Android 7 or earlier. Learn more about using the app
Yes, you can access Understanding NEC3: Engineering and Construction Short Contract by Kelvin Hughes in PDF and/or ePUB format, as well as other popular books in Derecho & Derecho contractual. We have over 1.5 million books available in our catalogue for you to explore.