This topical and timely book presents and innovative approach to dealing with the complexities of cost planning in PFI.
PFI/PPP projects have a significantly different costing environment from conventionally procured projects, requiring cost analysts to use their expertise and innovative thinking to develop whole-life cost solutions that deliver value for money to the client, thus improving public building assets performance.
Abdelhalim Boussabaine provides a thorough grounding in the theory of PFI, from its early evolution through to examples of current projects. In particular, the rationale for private financing of public services, arguments for and against PFI and 'value for money' mechanisms are discussed. The book presents an innovative framework for whole-life value and calls for changes in the way whole life cycle value is perceived, created and exchanged.
Cost Planning of PFI and PPP Building Projects provides the reader with existing knowledge as well as present innovative thinking for future development and management of PFI/PPP cost planning processes. Given the importance and novelty of this book, academics, professionals, undergraduate and postgraduate students will find this book valuable.
Trusted byĀ 375,005 students
Access to over 1.5 million titles for a fair monthly price.
Chapter 1 The Rationale Behind the Private Financing of Public Projects
DOI: 10.4324/9780203018842-2
Introduction
The UK Government introduced the Private Finance Initiative (PFI) as a policy to allow and regulate privately financed public projects. The private sector playing a part in the financing, creation and operation of public services and built assets is not a new idea, as this initiative can be traced back over several decades. This chapter outlines the rise of PFI/PPP (publicāprivate partnerships) in the UK construction economy. It puts into perspective the rationale for and against the PFI procurement method and sets out some basic definitions and clarifies the difference between PPP and PFI terminology. It points out the benefits of publicāprivate partnerships, it discusses the value of cost planning PFI/PPP projects and explains the challenges that are facing cost analysis in pricing long-term contracts. The chapter hopes to lay the ground for the subsequent chapters where the real in-depth analysis of the issues surrounding the cost planning of PFI/PPP projects lies.
What is PFI/PPP?
Lack of uniform agreement on the meaning of PFI/PPP creates confusion, introduces ambiguity and may lead to contractual disputes. If a precise definition is not agreed, it will be very difficult to measure the success or otherwise of this mode of project procurement and financing. Hence, this section presents the definition of PFI and PPP. Publicāprivate partnerships (PPP) were introduced by the UK Government to deliver modern, high-quality public services and to promote the UK's competitiveness. Any collaboration between the public authorities and the private sector is referred to as a partnership. Partnering is defined by the National Audit Office (NAO 1999a) as: āThe situation where a public organisation and a private one work together to provide a service with some sharing of risk and reward, usually over a period of time.ā
According to the Treasury (HMT 2000a) PPPs are a form of long-term relationship between the public and private sector for the benefit of both parties and cover a wide range of business partnership arrangements including joint ventures, concessions, sale of equity stakes in state-owned businesses, PFIs, franchises and outsourcing of public services. 4Ps (2006) defined and explained the purpose of PPP as follows:
Publicāprivate partnerships (PPPs) are a generic term for the relationships formed between the private sector and public bodies often with the aim of introducing private sector resources and/or expertise in order to help provide and deliver public sector assets and services. The term PPP is used to describe a wide variety of working arrangements from loose, informal and strategic partnerships to design, build, finance and operate (DBFO) type service contracts and formal joint venture companies.
It is clear from the above that PPP is broader in concept than PFI. But PFI is considered as a form of PPP. The House of Commons Select Committee on Treasury (2002) defined PFI as follows:
The principle of PFI is that a public sector body (central or local government or part of the health service, generically called āthe authorityā) obtains a service rather than an asset. A private sector contractor (often specially created for the purpose) funds any asset required and is then paid for the service provided. Usually payments will be made by the commissioning authority, but in some projects (e.g. a toll bridge) they are made by the public. There is also the possibility of charges to the public being subsidised by payments by the commissioning authority (e.g. a railway where the fares are subsidised for public benefit reasons). Normally, therefore, the commissioning authority will avoid the need for capital expenditure at the beginning of the project in exchange for making payments for the service as it is delivered, often over a period of up to thirty years. The private finance is temporary: the public sector still pays in the end. Because the contractor is paid for the service provided, it should be possible to arrange that he is taking the risks inherent in the construction of the asset.
In 1995, the UK Chancellor of the Exchequer gave the following description of PFI in his Budget speech:
Under the PFI the public sector does not simply sign a contract to buy a prison, a train or a computer system. It pays to have specific services supplied at guaranteed levels of performance. The government chooses the quality services the public require, and then goes out and acquires those services from private companies with the finance and expertise to deliver.
The Private Finance Panel (1995) defined PFI as follows:
PFI has become one of the government's main instruments for the delivery of high quality and cost effective public services. It enables value for money and improvements to be obtained by requiring the private sector in competition to be innovative in the design and operation of asset-based services, manage an appropriate level of risk and adequately maintain assets on a long-term basis.
The NAO definition emphasises the issues of procurement, management of public services and lack of funding for public projects:
A policy introduced by the Government in 1992 to harness private sector management and expertise in the delivery of public services ā¦
The PFI approach can enable departments to undertake projects which they would be unable to finance conventionally.
(NAO 1999a)
PFI is now established as a major form of Government procurement ⦠PFI has introduced changes in the way public services are procured and managed.
(NAO 2001)
Broadbent and Laughlim (2003) explained:
PFI, in its purest form, is a design build finance and operate (DBFO) system. It usually involves the provision, by a private sector consortium, of property-based services for a period of a minimum 30, and, more usually, 60 years, to a public sector āpurchaserā. In exchange for these services over this 30/60-year time horizon, the public sector pays a monthly, in effect, lease cost to the private sector supplier. This monthly cost is revised periodically as the contract progresses.
It is apparent from the above quotations that PFI evolved from the development of publicāprivate partnerships. Hence, hereafter, in this book, PFI and PPP are treated synonymously.
In examining the above quotations on PFI and PPP, one can identify the following key concepts that lead to the emergence of PFI/PPP:
sharing risk and reward;
introduction of the resources and expertise of the private sector into the public sector;
delivery of public services by the private sector at a guaranteed level of performance;
delivery of high quality and cost-effective public services;
innovation in the design and operation of assets;
risk transfer;
introduction of a new form of managing and procuring public services and projects;
long-term contractual agreements between private and public sectors;
a substitute for public expenditure control;
value for money in the delivery of public services.
The rationale for PFI/PPP has evolved over time to address these issues. While some of these concepts were instrumental in the materialisation of PFI/PPP, more recently the emphasis has shifted towards the theory that PFI/PPP is a public procurement system that can deliver value for money and manage risk transfer to the benefit of the public sector. Hence, this chapter seeks to provide an overview of PFI/PPP and the arguments relating to it.
The rise of PFI/PPP in the UK construction economy
The rise of PFI/PPP in the Western construction economy is not a new phenomenon. Many Western countries have used this procurement method to build motorways, prisons and hospitals. For example, in France, private financing for motorways was introduced in the late 1960s and early 1970s. Similar initiatives were also undertaken in Spain and Italy in the early 1970s. The following subsection will map out the process of PFI/PPP emergence in the UK. The development of PFI over the past 25 years is mapped out in Figure 1.1.
PFI/PPP post-1980
During the 1980s, the provision of private finance for public projects was governed by the Ryrie Rules (Ryrie was a Treasury official). The Ryrie Rules set two main criteria for the use of private finance in the procurement of public sector capital projects. These are:
Public sector capital projects can only be financed by the private sector if it is proved to be more costāeffective than a comparable publicly funded project.
The investment or asset must be part of the planned public sector schemes and not in addition to (in some cases, this rule is ignored by decision-makers). The consequences of this second rule are that public expenditures ought to be reduced by the same value as private investments.
Only a limited number of projects have been conceived under these two rules. Among these projects include the third crossing of the Thames at Dartford and the second Severn crossing. Many authors and politicians have commented that these rules have been a huge obstacle to encourage public authorities to seek private funding. This led to the abolishment of the second rule in 1989 by the UK Treasury which had the effect that privately funded projects no longer had to be substitutional. Finally, both rules were discarded in 1992 with the introduction of the PFI/PPP in the procurement of public services.
Figure1.1 Map of PFI/PPP development.
PFI/PPP post-1990
In the early 1990s, the UK economy suffered a considerable slowdown. This reflected on the ability of the government to raise sufficient tax revenue to adequately improve the public sector's infrastructure and services. This directly or indirectly led to the creation of new legislation for the introduction of private finance to develop and operate public services and assets:
The cumulative effect of under-investment on the capital stock inevitably increases through time. It was the reality of this pressing infrastructure need, alongside the equally pressing requirement to keep public expenditure under control, which, when coupled with an ideological commitment to involve the private sector in the public sector, led the Conservative Government to launch PFI in 1992.
(Broadbent and Haslam 2000)
PFI was launched in 1992 by the Chancellor of the Exchequer. This launch was met with little enthusiasm by the private sector. As a result, in 1993, the Chancellor gave the PFI greater emphasis and momentum. He announced the creation of a Private Finance Panel. The main aim of this panel is:
To encourage greater participation in the initiative by both private and public sectors, to stimulate new ideas, to identify new areas of public sector activity where the private sector could get involved, and to seek solutions to problems which might impede progress.
(Private Finance Panel 1995)
In 1994, the Chancellor insisted that the Treasury would not approve any capital project unless the options to acquire private funding had been explored by the procuring department. This universal testing decision had the effect that public sector authorities are forced to engage with the private sector. This decision has played a pivotal role in securing private funding for the development of services and assets in the public sector. In 1996, the local association established the PublicāPrivate Partnerships Programme (4Ps). The aim of 4Ps is to assist local authorities and encourage the growth of private investment in public services. Even with these initiatives, the uptake of PFI/PPP by the private sector fell short of the government's hopes. In 1997, after the general election, the new Labour Government re-affirmed its commitment to the PFI/PPP paradigm and appointed a committee to conduct a wide-ranging review of PFI/PPP. The new government also abandoned the universal testing of private sector financing in May 1997. The review committee made several key recommendations. Among these were:
abolishment of the Private Finance Panel;
control of PFI by the HM Treasury;
compulsory not to shortlist more than four bidders;
formation of a new private taskforce. The advice is that this entity should have a limited life and provide both strategic policies on PFI and technical advice on design and approval of specific projects.
These key recommendations led to centralisation and standardisation of practices across procuring departments. As a consequence of the review and formation of the Taskforce, the following have been achieved:
1998 The step-by-step guide to the PFI procurement process was launched.
1998 Development of a comprehensive approach to PFI training. A training programme on how to undertake PFI schemes was put in place.
1999 Standard contract guidance was issued.
1999 Agreement on accounting procedures for PFI schemes was reached.
1999 Establishment of a review group to sign off all local authority PFI schemes.
Other major developments in 1999 were the announcement and launch of a second review on PFI/PPP by the government. The main recommendations from the second review are:
Formation of an advisery body composed of private sector experts to replace the technical advisery wing of the Treasury Taskforce.
All PFI standard documentation ha...
Table of contents
Cover Page
Half-Title Page
Other
Title Page
Copyright Page
Dedication
Contents
List of figures
List of tables
Preface
Acknowledgements
List of abbreviations
Part I PFI/PPP and VFM Rationale
Part 2 Procuring Building Assets Under the PFI/PPP Model
Part III The Process of Cost Planning of PFI/PPP Projects
Part IV Cost Variations in PFI/PPP Projects
Part V Risk in Costing PFI/PPP Projects
Bibliography
Index
Frequently asked questions
Yes, you can cancel anytime from the Subscription tab in your account settings on the Perlego website. Your subscription will stay active until the end of your current billing period. Learn how to cancel your subscription
No, books cannot be downloaded as external files, such as PDFs, for use outside of Perlego. However, you can download books within the Perlego app for offline reading on mobile or tablet. Learn how to download books offline
Perlego offers two plans: Essential and Complete
Essential is ideal for learners and professionals who enjoy exploring a wide range of subjects. Access the Essential Library with 800,000+ trusted titles and best-sellers across business, personal growth, and the humanities. Includes unlimited reading time and Standard Read Aloud voice.
Complete: Perfect for advanced learners and researchers needing full, unrestricted access. Unlock 1.5M+ books across hundreds of subjects, including academic and specialized titles. The Complete Plan also includes advanced features like Premium Read Aloud and Research Assistant.
Both plans are available with monthly, semester, or annual billing cycles.
We are an online textbook subscription service, where you can get access to an entire online library for less than the price of a single book per month. With over 1.5 million books across 990+ topics, weāve got you covered! Learn about our mission
Look out for the read-aloud symbol on your next book to see if you can listen to it. The read-aloud tool reads text aloud for you, highlighting the text as it is being read. You can pause it, speed it up and slow it down. Learn more about Read Aloud
Yes! You can use the Perlego app on both iOS and Android devices to read anytime, anywhere ā even offline. Perfect for commutes or when youāre on the go. Please note we cannot support devices running on iOS 13 and Android 7 or earlier. Learn more about using the app
Yes, you can access Cost Planning of PFI and PPP Building Projects by Abdelhalim Boussabaine in PDF and/or ePUB format, as well as other popular books in Architecture & Architecture Methods & Materials. We have over 1.5 million books available in our catalogue for you to explore.